Bengaluru, Karnataka – The ambitious ropeway project at Nandi Hills, a popular tourist destination near Bengaluru, continues to navigate a complex web of regulatory approvals and environmental concerns, even as construction activities gain momentum. Despite significant progress in land acquisition and preparatory works, the project awaits final clearance from the Union Ministry of Environment, Forest and Climate Change, with the Karnataka Forest Department having granted conditional approval.
Environmental Concerns and Forest Clearances
The Nandi Hills ropeway, envisioned to alleviate traffic congestion and enhance tourism, requires approximately 0.86 hectares of forest land. While the State Forest Department has recommended the project to the Centre, citing that the proposed corridor does not traverse a national park or wildlife sanctuary, the Union Ministry has requested additional information, specifically a Wildlife Mitigation Report. This has led to further delays in the final approval process. Environmental activists and conservationists have voiced strong objections, warning of potential ecological damage, including impacts on soil stability and local bird habitats. Concerns have also been raised about the structural integrity of the hills, with fears that drilling for the ropeway could cause damage. Critics argue that the development projects, including the ropeway, are being undertaken without adequate scientific assessment of their environmental impact, potentially harming the delicate ecosystem of the hills which are also a crucial source of water for several rivers in the region.
Project Progress and Proposed Timeline
The Karnataka State Tourism Development Corporation (KSTDC) is spearheading this public-private partnership initiative. The project, which includes a 2.93-kilometer ropeway, aims to connect the lower and upper terminals of Nandi Hills with 50 semi-closed cabins. The lower terminal is planned to feature extensive parking facilities for vehicles and a waiting area for up to 600 people. Construction work, contracted to Dynamicx Ropeway Private Limited, is expected to take approximately 18 to 24 months once all approvals are secured and land handover is complete. While initial estimates suggested a completion target by mid-2027, recent directives from the state’s Energy and Tourism Minister KJ George aim to accelerate the implementation of this and other ropeway projects across Karnataka, urging for expedited approval processes. The foundation stone for the project was initially laid in 2023, but it has faced several procedural and technical hurdles, including land acquisition and forest clearances, since then.
Addressing Tourism Pressures
Nandi Hills, situated in the Chikkaballapur district, experiences significant footfall, particularly on weekends, leading to substantial vehicular congestion and environmental strain. The ropeway is projected to offer a more sustainable and efficient mode of transport to the summit, reducing the carbon footprint associated with the thousands of vehicles that currently ascend the hills. The project also includes plans for modern terminal buildings with amenities like food courts and improved parking facilities at the base to manage tourist influx. Authorities have assured that construction activities will prioritize minimal ecological disturbance and that land acquisition, including private parcels for the upper terminal, is nearing completion. The state government is also preparing a comprehensive mobility plan to regulate private vehicle access during peak times, reinforcing the ropeway as a primary access solution.
❤️ Support Independent Journalism
Your contribution keeps our reporting free, fearless, and accessible to everyone.
Or make a one-time donation
Secure via Razorpay • 12 monthly payments • Cancel anytime before next cycle


(We don't allow anyone to copy content. For Copyright or Use of Content related questions, visit here.)

The Chenab Times News Desk