The Punjab government has initiated a significant flood management project for the Swan River in Ropar district, involving an investment of Rs 161.75 crore. The project aims to construct permanent embankments along vulnerable sections of the river to safeguard agricultural land, residential areas, and infrastructure from potential devastation during the monsoon season.
Information was available with The Chenab Times that despite the project receiving necessary approvals and tenders being invited for its 41 components, the acquisition and transfer of land required for the embankments have posed a notable challenge, delaying its progression.
The Swan River, originating in Himachal Pradesh, flows through Una district before entering Punjab and joining the Sutlej near Sri Anandpur Sahib. The river spans approximately 85 km, with 65 km in Himachal Pradesh and 20 km in Punjab. Its catchment area covers about 1,400 square kilometres, primarily in Himachal Pradesh’s Una district and Punjab’s Ropar district.
The project report, prepared by the Water Resources Department, outlines the construction of embankments stretching from the Punjab border, downstream of the Santokhgarh bridge in Himachal Pradesh, towards the river’s confluence with the Sutlej. Specifically, the plan includes embankments along 66,000 metres on the left bank and 61,000 metres on the right bank. These sections have been identified as highly susceptible to floodwater overflow, posing a substantial risk to nearby villages, agricultural fields, and other assets.
The Swan River is particularly prone to sudden increases in water discharge during the monsoon. According to the project report, an estimated 3,344 hectares of agricultural land in Ropar district are at risk of flooding. Furthermore, approximately 776 hectares of fertile agricultural land currently remain uncultivated due to the persistent threat of recurring floods.
The proposed Swan River Flood Management and Integrated Land Development Project is designed to reinforce and elevate the riverbanks through the construction of scientifically engineered embankments on both sides. The project’s execution has been meticulously divided into 41 distinct estimates, all of which have received approval from the competent authority. Tenders for all these works have been formally invited, according to Minister for Education Harjot Singh Bains, who also represents the Anandpur Sahib Assembly constituency.
Minister Bains stated that elements within the mining lobby were attempting to create obstacles for the Swan channelisation project in the Anandpur Sahib region. He asserted the government’s unwavering commitment to the project’s implementation, highlighting its potential to protect the area from flash floods, curb illegal mining activities, and improve the local water table.
However, the project report acknowledges that land acquisition and transfer for the construction of these crucial embankments are still pending. The department is actively engaged in efforts to sensitise landowners about the project’s objectives and anticipated benefits, aiming to encourage their cooperation in making the necessary land available to facilitate the timely execution of the development works.

The Chenab Times News Desk