The National Green Tribunal (NGT) has ordered the formation of a joint committee to investigate alleged encroachments and illegal constructions on the riverbed and floodplains of the Salani river near Nahan in Himachal Pradesh’s Sirmaur district. The committee is empowered to undertake demolition if violations are detected and to impose environmental damage compensation.
Information was available with The Chenab Times indicating that a Bench comprising Justice Prakash Shrivastava, Chairperson, and Dr Afroz Ahmad, Expert Member, heard the matter. The tribunal reviewed allegations that respondents had failed to adhere to an undertaking provided on January 12, 2016, which stipulated the removal of existing construction in Sainwala village and the restoration of the riverbed area.
Joint Committee to Inspect and Act
The NGT took note of the presented evidence and subsequently constituted a joint committee. This committee will include the Member Secretary of the Central Pollution Control Board (CPCB) and representatives from the Regional Office of the Union Ministry of Environment, Forest and Climate Change, based in Chandigarh. The Deputy Commissioner of Sirmaur has been designated as the nodal agency responsible for coordinating and ensuring compliance with the joint committee’s directives.
The committee has been instructed to visit the Salani river site to assess the extent of construction purportedly carried out in contravention of the undertaking given to the Tribunal. Furthermore, the Deputy Commissioner of Sirmaur has been directed to initiate appropriate measures for the demolition of any identified illegal constructions, following a hearing opportunity for the respondents involved.
Environmental Damage Compensation to be Assessed
In addition to the inspection and demolition orders, the NGT has directed the Himachal Pradesh State Pollution Control Board to investigate past violations related to the breach of the undertaking. Should any such violations be substantiated, the pollution control board is mandated to determine and levy environmental damage compensation. This assessment will also require providing the respondents with an opportunity to be heard. The Himachal Pradesh State Pollution Control Board is required to submit its action-taken report to the Registrar General of the Tribunal.
The NGT also noted that the floodplains of the Salani river had still not been demarcated, a commitment made under the earlier undertaking. The respondents themselves admitted that fresh construction had taken place and the floodplain zone had not yet been officially defined. The Deputy Commissioner, Sirmaur, has been tasked with submitting a comprehensive action taken report to the Registrar General of the NGT within a period of four months.

The Chenab Times News Desk